Located in the City’s northeast quarter, Mountview has historically faced stormwater flooding and sanitary sewer backups.

Between 2020 and 2023, the City completed nearly $2 million in neighbourhood stormwater infrastructure improvements to reduce surface flooding and basement backflow risk, including:

  • 32 new storm structures
  • More than half a kilometre of new storm pipe
  • Two underground storm chambers
  • One outfall structure

In June 2026, the City awarded a contract for the Mountview Storm & Sanitary Modelling project to further investigate localized sanitary sewer backups. The study will:

  • Improve understanding of Mountview’s stormwater and sanitary sewer systems
  • Identify the root causes of basement sewer backups and surface flood risks
  • Collect and incorporate local resident input
  • Recommend infrastructure improvements and provide high-level cost estimates to reduce neighbourhood sewer backup risk

Stakeholder engagement will include consultation with local residents and user groups. A resident survey has been developed to gather feedback for the study.

Phases

Phases overview
Phase 1: Historical Construction Phase 1 Summary
Historical Construction Phase 1 Summary
Phase 2: Historical Construction Phase 2 Summary
Historical Construction Phase 2 Summary

Historical Construction Phase 2 Summary

January 1, 2023 6:00 a.m. - December 31, 2023 5:59 a.m.

Phase 2 focused on water coming into the neighbourhood from the east and commenced work at 96A St and the laneway running into the Phase 1 construction.

  • Over 392 m of new storm sewer installed
  • Nine catch basin manholes
  • Eight manholes
  • One storm chamber